Overview of the project
Overview of the project
Channel 19 duck tip and concrete band
Channel 19 duck tip and concrete band

Employer:

  • Amir Kabir Agriculture Company

Consultant:

  • Pajabnegar Consulting Engineers Co

Contractor:

  • Tavan Sazeh Eglim Company

project cost:

  • 17,576,594,903 rials

The main goals of the project:

  • Returning the used water of the sugar factory to the irrigation system of agriculture and industry
  • Preventing 4 cubic meters per second of water that can be used for irrigation from entering the drainage system

Project location:

  • 55 km south side of Ahvaz city
A view of the pumping station and electrical room
A view of the pumping station and electrical room
Output structure of the pumping station