Implementation of water storage pond
Implementation of water storage pond
General view of the pump area
General view of the pump area
A view of the work execution steps
A view of the work execution steps

Employer:

  • Management of agricultural jahad of Shushtar city

Consultant:

  • Pajabnegar Consulting Engineers Co.

contractors:

  • Sinab Zende Roud Company (supply of items and main project implementer)
  • Mazand Noor Electrical Engineering Company (executor of the electrical part of the project)
  • Miras Karan Hamon Company (executor of project completion works)
  • Karun Khuzestan Company (providing mechanical items for the project)

The main goal of the project:

  • Completing the capacity and height of water pumping in the irrigation network under the pressure of Guriye farms F6 and F5

Project location:

  • Guriye region , 25 kilometers south of Shushtar city